Engine Removal Forecast
To effectively manage the TotalCare Services Agreement, it is essential that engine removals are planned to the fullest extent possible. A regular meeting will be held between the Customer Support Team and Customer to discuss engine removal forecasts.
As far as possible, engines should be removed in accordance with the agreed removal forecast. For Rolls-Royce and Customer obligations, refer to Schedule 5 Part 5 of the TotalCare Agreement.
Engine Removed
CustomerPowerplant notify R-R of engine removal. Provide required OFFLOG with notification within 10 days with the following requirements
Prepare Engine for Dispatch
CustomerPrepare engine in accordance with Transportation Standard and arrange transportation to OHB. Refer to the Engine Transportation section for detailed transportation requirements.
Provide Final Engine Data
CustomerSubmit Final Engine Data within 10 days of removal and provide Additional Services instructions if applicable
OHB Finalizes
OHBOverhaul base receives engine and finalizes induction slot
Conduct TRC
CombinedTechnical Review Committee conducted prior to engine induction
Engine Workscope Completed
CombinedFinal workscope agreed and executed
Engine Release
CustomerCustomer arranges engine transportation within the agreed timeframe of engine release
OFFLOG — Required Information at Removal
Required within 10 days of engine removal
- Purchase order addressed to Rolls-Royce TotalCare Services Limited requesting Repair
- Aircraft Registration
- Engine Position
- Engine S/N removed / installed
- Removal reason
- Total Time/Total Cycles of Engine removed
- Station and date of removal
Includes: Engine/Module Lives, Carry Forward, Oil Uplift History, LRU Listing, SB/NMSB Listing...
Key Timelines
Per Contract
Submit preliminary engine data post removal
Per Contract
Arrange engine transportation after release
Regular
Customer Support Team and Customer forecast meetings
Process Actors
Customer
Powerplant / Airline operations
Rolls-Royce
Customer Support Team and planning teams
OHB
Overhaul Base facility
Combined
Joint responsibility (e.g., TRC)
Technical Review Committee
The TRC is conducted to review engine data, agree on workscope, and ensure alignment between all parties before shop visit execution.
Planning Best Practice
Submit preliminary engine data to the R-R Customer Support Team within 10 days of engine removal to facilitate timely preparation of workscopes and avoid delays in the shop visit process.